COMPANY EXPERIENCE
POWER PLANT PROJECTS (ENCLOSURE)
| NO | PROJECT | CLIENT | YEAR | SCOPE |
| 1 | PLN Jatirangon | PT. Siemens Indonesia | 2004 | Free Standing SS3000 |
| 2 | Pluak Daeng Power Plant | PT. Siemens Indonesia | 2005 | Free Standing SS3000 |
| 3 | PLN Ciamis | PT. Siemens Indonesia | 2005 | Marshaling Kios |
| 4 | Ha Tinh Power Plant | PT. Siemens Indonesia | 2005 | Free Standing SS3000 |
| 5 | PLN Karawang Baru | PT. Siemens Indonesia | 2005 | Free Standing SS3000 |
| 6 | PLN Bandung Selatan | PT. Siemens Indonesia | 2005 | Marshaling Kios |
| 7 | PLN Sunyaragi | PT. Siemens Indonesia | 2005 | Marshaling Kios |
| 8 | PLN Sentul | PT. Siemens Indonesia | 2005 | Free Standing SS3000 |
| 9 | Vietnam | PT. Siemens Indonesia | 2007 | Free Standing SS3000 |
| 10 | Transformer | PT. Pauwels Trafo Asia | 2007 | Cubicle |
| 11 | Transformer | PT. PauwelsTrafo Asia | 2008 | Cubicle Steel, Cubicle SS316 |
| 12 | Add Quang Ninh Project | PT. Siemens Indonesia | 2008 | RCP + Acessories |
| 13 | Local Parts for QuestGivaudan | PT. Siemens Indonesia | 2008 | NCE SS316 |
| 14 | Thang Long : BD dan WBS | PT. Siemens Indonesia | 2008 | Acessories |
| 15 | Muara Karang | PT. Siemens Indonesia | 2008 | RCP |
| 16 | Masaran Substation | PT. Siemens Indonesia | 2008 | VATECH |
| 17 | 34OP-83066.P.50&34OP-83068.P.50 | PT. Siemens Indonesia | 2008 | NCE Steel |
| 18 | Project DONG HOA & TRANG BACH | PT. Siemens Indonesia | 2008 | RCP SS3000 |
| 19 | Seputih Banyak | PT. Siemens Indonesia | 2008 | RCP |
| 20 | 2x40 MVA Cory Mine | PT. Unelec Indonesia | 2008 | NCE SS316L |
| 21 | Arkadia | PT. Siemens Indonesia | 2008 | NCE Steel |
| 22 | ST. Croix | PT. Unelec Indonesia | 2008 | NCE SS304 |
| 23 | Lolak & Kotamobagu | PT. Siemens Indonesia | 2008 | Marshaling, RCP |
| 24 | PLN P3B | PT. Unelec Indonesia | 2008 | NCE SS304 |
| 25 | Vietri | PT. Siemens Indonesia | 2008 | VT-Box, Marshalink |
| 26 | Soc Trang | PT. Siemens Indonesia | 2008 | Outdoor Enclosure |
| 27 | Sidi Krir & El Atf | PT. Siemens Indonesia | 2008 | RCP |
| 28 | PLTU Rembang | PT. Unelec Indonesia | 2008 | Junction Box |
| 29 | United Group 3.5mVA (MPT) | PT. Unelec Indonesia | 2008 | NCE Steel |
| 30 | Yarwun 4.3mVA (MPT) | PT. Unelec Indonesia | 2008 | NCE SS316 |
| 31 | PLN Cilacap | PT. Fajar Surya Cipta | 2008 | Free Standing SS304 |
| 32 | IBRD 2B, KE3 LOT6 & SULUT | PT. UNELEC INDONESIA | 2008 | Junction Box |
| 33 | SURALAYA | PT. GUNA ELEKTRO | 2009 | Wall Mounting |
| 34 | GI 150kV Maros | PT. Siemens Indonesia | 2009 | Marshaling Kiosk |
| 35 | Benin | PT. Unelec Indonesia | 2009 | Wall Mounting |
| 36 | Middletown 66MVA, USA | PT. Unelec Indonesia | 2009 | Wall Mounting |
| 37 | Add. Dong Ha + Muara Karang | PT. SIEMENS | 2009 | Free Standing SS3000 |